1999 PCED On Board Diagnostics II
SECTION 5: Pinpoint Tests

KL: Shift Indicator Lamp (SIL)
  KL: Introduction  

 

KL1 CHECK SHIFT INDICATOR LAMP OPERATION

Is SIL on all the time?
Yes No
KEY OFF. GO to KL4 . KEY OFF. GO to KL2 .
 

KL2 CHECK SIL CIRCUIT FUSE

Is fuse OK?
Yes No
INSTALL SIL circuit fuse. GO to KL3 . REPAIR short circuit. REPLACE SIL circuit fuse.
 

KL3 CHECK SIL BULB

Is SIL bulb OK?
Yes No
GO to KL5 . REPLACE SIL bulb.
 

KL4 CHECK SIL CIRCUIT FOR SHORT TO GROUND IN HARNESS

Is resistance greater than 10,000 ohms?
Yes No
REPLACE PCM (refer to Section 2 , Flash EEPROM). REPAIR short circuit.
 

KL5 CHECK IGN START/RUN VOLTAGE TO SIL SOCKET

Is the voltage greater than 10.5 volts?
Yes No
KEY OFF. GO to KL7 . KEY OFF. RECONNECT SIL bulb. GO to KL6 .
 

KL6 CHECK OPERATION OF TOP GEAR SWITCH

Is resistance less than 5.0 ohms?
Yes No
REPAIR open circuit. REPLACE top gear switch.
 

KL7 CHECK SIL CIRCUIT FOR OPEN IN HARNESS

Is resistance less than 5.0 ohms?
Yes No
REPLACE PCM (refer to Section 2 , Flash EEPROM). REPAIR open circuit.